2020 - 2020

Sharbatly Building

Client: Ministry of Transportation Scope: Structural Strengthening Location: Giza, Egypt

An emergency structural rehabilitation following major soil settlement caused by a tunnel boring machine malfunction near the Sharbatly Building, resulting in column failure and extensive cracking in walls and footings. Cause TBM malfunction -> Soil Settlement -> Column failure and structural cracking Intervention Measures
  • Installation of new micropile foundations
  • Soil injection, and ground improvement
  • Construction of new reinforced concrete walls
  • Concrete jacketing for columns and beams.
Execution Duration Completed within 3 weeks